Sustainability performance at our sitesHartlepool

Hartlepool 20" Pipe Mill is located in the North East of England with an annual production capacity to produce 220,000 tonnes of tube products for the construction, engineering, and energy and power markets.


Hartlepool

Hartlepool 20" Pipe Mill is located in the North East of England with an annual production capacity to produce 220,000 tonnes of tube products for the construction, engineering, and energy and power markets.

The Hartlepool site was awarded first place at the 2016 Tata Steel Excellence awards for the Green Award with a proactive approach to the environment which has provided a vehicle for change.  The environmental plan drove costs down to increase competitive edge of the site through water and energy consumption reduction and improved safety and welfare concerns through noise and dust reductions.

Greenhouse gas emissions

Resource use and waste management

Water extraction

Transport impacts

Employment and skills

Local communities

Performance data

Greenhouse gas emissions

The only greenhouse gas emissions from Hartlepool 20" Mill are emissions of carbon dioxide resulting from the combustion of natural gas in forming and heat treatment processes. Indirectly, the site contributes to CO2 emissions associated with the consumption of electricity for conveyance, pumping, cooling etc.

Key focus areas for reduction in CO2 relate to the efficient use of natural gas on furnace operations and electrical efficiency. Initiatives include:

  • Installation of a new, highly efficient induction welder which uses less electrical energy
  • Improvements made to the furnace to reduce heat losses and fugitive emissions
  • Flexibility of the workforce to allow breaks during load management periods
  • Nightly energy audits carried out by the shift engineers to ensure all unnecessary equipment/ lights/ heaters are turned off when not in use.
  • New Variable Speed fans fitted to the RHS furnace to improve energy performance
  • Plans furnace door improvements

Hartlepool is covered by a new energy efficiency governance process established within Tata Steel Europe, whereby its energy performance has been compared to a benchmark as part of a gap analysis exercise. The site has generated a range of schemes aimed at bridging the gap with best practice. Internal targets for improvement have been established and Tata Steel Europe’s Chief Technical Officer and his direct reports review the progress of each site towards these on a quarterly basis.

Back to top

Resource use and waste management

In line with our objective to reduce / eliminate wastes to landfill, we have enacted a number of waste reduction strategies at our Hartlepool plant, as a result of which it has now achieved very high recycling rates, with only an insignificant tonnage of difficult waste unrecovered. It has trained Environmental Representatives to carry out audits on issues such as waste segregation around site to support this and targets are reviewed on a quarterly basis.

Back to top

Water extraction

We have enacted a number of improvements to optimise water consumption, for example:

  • Reuse of surface water collected in an on-site reservoir, for use around site for dust suppression
  • Water used for NDT purposes is cooled and re-used within the production system
  • Use of open evaporation cooling tower systems to cool re-circulating water in order to minimise raw water use
  • Monitoring of potable and industrial water use to quickly identify leaks and initiate repairs

Hartlepool has recently won an Anglian Water 'Save Every Drop' award for reducing leaks from 12.5 litres/ second four years ago to 0.85 litres/ second.

Back to top

Transport impacts

Transport impacts are managed centrally within Tata Steel and, as such, it is not possible to disaggregate the transport impacts associated with the production and delivery of specific products from specific locations from the total estimate of Tata Steel transport impacts.

  • As shipping and logistics activities are managed centrally within Tata Steel it is not possible to disaggregate the CO2 emissions associated with the production and delivery of specific products from specific locations from the total estimate of Tata Steel transport impacts. See the general page for information on Tata Steel’s transport impacts and some of the steps we are taking to reduce these.

Back to top

Employment and skills

We apply a common approach to employment and skills at all, of our sites. See the general page for information on what Tata Steel is doing to advance the learning and development of its employees.

Back to top

Local communities

Hartlepool engages in a range of community initiatives, for example:

  • Building relationships with local schools and colleges, facilitating work experience placements, offering engineering apprenticeships
  • Supporting local charities and organising fundraising activities such as sponsored walks and the ‘Great North Run’
  • Fundraising and collection of dog food, blankets and toys for a local 'Stray Aid' dog shelter
  • Noise reduction measures, including roof access door replacement
  • Planned furnace door improvements

Back to top

Performance data

Hartlepool 20" Mill   2014 2015 2016
CO2 emission (t) Verified EU ETS 13,767 14,673 12,598
Worldsteel scope 20,190 21,980 19,103
Water use (m³) 62,030 70,175 76,627
Waste disposed (t) (% of waste produced) 15 0% 16 0% 18 0%
Waste recovered (t) (% of waste produced) 18,866 100% 16,470 100% 14,836 100%
Justified complaints (n) 4 3 1

*internal metrics used for period before site was in EU ETS scope

Back to top