St Paul's Square, Liverpool

Installed - February 2007

Corefast enabled Shepherd Construction to save 21 weeks on a 105-week programme at its St Paul’s Square, Liverpool development. Its use reduced the number of tower cranes required on site from two to one and delivered significant cost savings.

Project Summary images - SPSq_pp1.jpgProject Summary images - SPSq_pp2.jpg

Corus’ rapid erect modular Bi-Steel building core system was specified for the lift/stair cores in the striking 17,000m², eight-storey office building which is part of phase two in this city-centre mixed use development scheme.

The construction programme was reduced from the originally estimated 105 weeks using a traditional core construction technique to 84 weeks using Corefast. 

In addition, by selecting Corefast only one tower crane was required instead of the two specified in the original design, and due to Corefast’s stiffness and rigidity the number of structural cores needed was reduced from five to three - providing significant cost savings.

     

Construction Hotline

+44 (0) 1724 40 50 60
Or click here to contact us 

Tata Steel Projects - Birmingham Office

Alpha Tower

Suffolk St

Birmingham B1 1TT

United Kingdom


T  +44 (0)121 2421240

F  +44 (0)121 2464664

E  bi-steel@ tatasteel.com


[View map]

Fact file

Client:

English Cities Fund

Architect:

RHWL Partnership

Main Contractor:

Shepherd Construction

Structural Engineer:

Buro Happold

Steelwork Contractor:

Billington Structures