Skip navigation

Panels and Profiles

Transport and handling

Receiving Decking
Composite Floor Decking is packed into bundles of up to 24 sheets, and the sheets are secured with metal banding. Each bundle may be up to 950mm wide (the overall width of a single sheet) by 750 mm deep, and may weigh up to 2.5 tonnes, depending on sheet length (average weight is about 1.5 tonnes). Loads are normally delivered by articulated lorries approximately 16 m long with a maximum gross weight of up to 40 tonnes, and a turning circle of approximately 19 m. The Main Contractor should ensure that there is suitable access and appropriate standing and off-loading areas.

Each bundle has an identification tag. The information on each tag should be checked by operatives from the decking contractor (or, if they are not on site, the Main Contractor) immediately upon arrival. In particular, the stated sheet thickness should be checked against the requirement specified on the contract drawings, and a visual inspection should be made to ensure that there is no damage.

Lifting Bundles
The bundles should be lifted from the lorry. Bundles should never be off-loaded by tipping, dragging, dropping or other improvised means. Care is needed when lifting the decking bundles; protected chain slings are recommended. Unprotected chain slings can damage the bundle during lifting; when synthetic slings are used there is a risk of the severing them on the edges of the decking sheets. If timber packers are used, they should be secured to the bundle before lifting so that when the slings are released they do not fall to the ground (with potentially disastrous results). Bundles must never be lifted using the metal banding.

Positioning the Decking
The support steelwork should be prepared to receive the decking before lifting the bundles onto it. The top surface of the underlying beams should be reasonably clean. When thru-deck welding of shear studs is specified, the tops of the flanges should be free of paint or galvanising. The identification tags should be used to ensure that bundles are positioned on the frame at the correct floor level, and in the nominated bay shown on the deck layout drawing. The bundles should be positioned such that the interlocking side laps are on the same side. This will enable the decking to be laid progressively without the need to turn the sheets. The bundles should also be positioned in the correct span orientation, and not at 90 o to it. Care should be taken to ensure that the bundles are not upside down, particularly with trapezoidal profiles. The embossments should be oriented so that they project upwards.

Placement of Decking
The breaking open of bundles and installation of decking should only begin if all the sheets can be positioned and secured. This will require sufficient time and suitable weather. The decking layout drawing should also be checked to ensure that any temporary supports that need to be in position prior to deck laying are in place. Access for installation will normally be achieved using ladders connected to the steel frame. Once they have started laying out the sheets, the erectors will create their own working platform by securely fixing the decking as they progress.

The laying of sheets should begin at the locations indicated on the decking layout drawings. These would normally be at the corner of the building at each level; to reduce the number of 'leading edges', i.e. unprotected edges, where the decking is being laid. When the bundles have been properly positioned, as noted above, there should be no need to turn the sheets manually, and there should be no doubt which way up the sheet should be fixed.

Individual sheets should be slid into place and, where possible, fixed to the steelwork before moving onto the next sheet. This will minimise the risk of an accident occurring as a result of movement of a sheet when it is being used as a platform. (However, for setting-out purposes, it may be necessary to lay out an entire bay using a minimum number of temporary’ fixings before fully securing the sheets later). Sheets should be positioned to provide a minimum bearing of 50 mm on the steel support beams. The ends of adjacent sheets should be butted together. A gap of up to 5 mm is generally considered not to allow excessive seepage, but, if necessary, the ends of the sheets may be taped together. When end gaps are greater than 5 mm, it is normally sufficient to seal them with an expanding foam filler. The longitudinal edges should be overlapped, to minimise concrete seepage.

Cutting Sheets
Where necessary, sheets may be cut using a grinder or a nibbler. However, field cutting should be kept to a minimum and should only be necessary where a column or other obstruction interrupts the decking. Gaps adjacent to the webs of columns should be filled in with off-cuts or thin strips of steel. Decking sheets shown as continuous on the decking layout drawing should never be cut into more than one length. Also, sheets should never be severed at the location of a temporary support, and the decking should never be fastened to a temporary support. As the work progresses, unwanted scraps and off-cuts should be disposed of in a skip placed alongside the appropriate level of working. The skip should be positioned carefully over a support beam to avoid overloading the decking If a skip is not available, scraps should be gathered for collection by the Main Contractor as soon as is possible. Partially used bundles should be secured, to avoid individual sheets moving in strong winds.

 

Contact

Shotton

Deeside

Flintshire

CH5 2NH

United Kingdom


T  +44 (0) 845 30 88 330

F  +44 (0) 845 30 11 013

E  sales.theworks@ tatasteel.com

E  technical.theworks@ tatasteel.com


My Order

 
Account Details

No
Yes