Tower crane mounted on top of Corefast core reduces build time

Tower crane mounted on top of Corefast core reduces build time

24 Jun 2008

This tower crane, mounted on top of a Corus Corefast building core, is being used to erect a second Corefast structural core as well as the main steelwork frame on this landmark office scheme in Mayfair, London.

Using this modular off-site core construction technique will enable construction manager Mace to save an estimated eight weeks on the project programme.

The tower crane was mounted onto a special steel ‘saddle’, designed and fabricated by Corus, which was bolted onto the top of the first Corefast core.  This innovative approach enabled Mace to erect the second Corefast core, a
Bi-Steel shear wall and the complete steel building frame without the limitations that a tower crane positioned within this very constrained city centre site would have presented.

Project Team

Developer: Pembroke Real Estate

Architect: RHWL Architects

Structural Engineer: Buro Happold

Construction Manager: Mace Ltd

Steelwork Contractor: Billington Structures

       

Construction Hotline

+44 (0) 1724 40 50 60
Or click here to contact us 

Tata Steel Projects - Birmingham Office

Alpha Tower

Suffolk St

Birmingham B1 1TT

United Kingdom


T  +44 (0)121 2421240

F  +44 (0)121 2464664

E  bi-steel@ tatasteel.com


[View map]

My Order

 
Account Details

No
Yes